Still remodelling…

Despite my best efforts, the bedroom remodelling is still going on. Here is the breakdown of the tasks:

  1. Paint the walls in the room
  2. Prime the trim and doors
  3. Paint the trim and the doors
  4. Install plugs, switches, and faceplates to match the trim
  5. Install crown moulding
  6. Caulk around the moulding and set the moulding brads
  7. Touch up trim and wall paint as needed
  8. Install new curtain rods and curtains
  9. Put room back together

I am finally in the home stretch now. My goal is finish with the caulking and painting by the end of Saturday night. That way, I can finish up Sunday morning with the curtains and moving the furniture back in place and, after three and a half weeks, we can finally move back into our bedroom.

3 Responses to “Still remodelling…”

  1. Geof F. Morris Says:

    You’ll get there, man. Hang in there!

  2. ashley Says:

    In the end, three and a half weeks will be worth it. It’s such a pretty color, and the new trim looks great :)

    Good job honey :)

  3. Experiments in Life Says:

    Project Master Bedroom: Completed

    Well, the master bedroom is finally finished. I started work on the project right around the end of December and here it is, late January, when I am finishing up. I originally estimated that it would take me four days to finish — it took more …

Leave a Reply